ALEMCO×Wynn Al Marjan Island
Wynn Al Marjan Island · BMS DDC Panel Progress Dashboard
Initialising…0%
ALEMCO in collaboration with Wynn Al Marjan Island · Data: DDC Podium & Tower WIR Status tracker
ALEMCO × Wynn Al Marjan Island / BMS / Overview

Project Overview

Sign out

Construction & commissioning pipeline

Panels that have passed each stage. Red stages are where work is piling up.

Key insights

Calculated live from the tracker

Where each panel stands today

Each panel placed at the first stage it has not yet passed

Completion by area

Construction complete vs. T&C complete

Level-by-level progress

Panels passed at each stage. Shade shows the share of the level's panels.

Level-by-level progress

Panels passed at each stage

Construction complete by BCC

Podium panels grouped by building control centre

Construction complete by ALEMCO PM

Area-wise project manager in charge

Construction progress by person

Panels under each person that are fully constructed

Where their panels stand

Status mix of each person's panels

People

Click a person to see their panels and blockers

Stage by stage

Approved (green), WIR raised but not approved (red) and in progress (yellow) at each construction stage

Where unbuilt panels are stuck

First construction stage each unfinished panel has not passed

Siemens installation & termination approval

Status recorded in the tracker for every panel

Construction blockers

Why unbuilt panels are held up, taken from the approval and containment notes

Unbuilt panels by level

Panels not yet construction-complete

Panels still in construction

Click a row for the full panel record

Constraint types

Click a type to filter the log below

Who needs to act

Worked out from the wording of each item

Equipment affected

Equipment named in the constraint text

Constraint log

The tracker's “Construction Remarks” column is empty, so these constraints are pulled from four places: notes typed into the stage cells instead of a WIR number, Podium containment notes, the Siemens installation & termination approval status, and WIRs raised but not approved (red cells). Only panels that are not yet construction-complete are included.

Constraint types

Click a type to filter the log below

Who needs to act

Based on the constraint type and wording

Stage being blocked

Where in the construction sequence each item sits

Constrained panels by level

Unbuilt panels with at least one constraint

Constrained panels by BCC

Unbuilt panels with at least one constraint

Construction constraint log

Containment is only tracked on the Podium sheet, so Tower panels are not included on this page.

Containment status

All 434 Podium panels

By level

Completed / total

By zone

Completed / total

By BCC

Completed / total

Containment targets

Panels with a target date that are not yet complete

Equipment energisation (ALEMCO)

Status recorded per panel

DDC testing status (Siemens)

Status recorded per panel

Construction complete, waiting on power

Finished by the BMS team but cannot be tested until ALEMCO energises them. Click a row for details.
ApprovedWIR raised, not approvedIn progressNot startedAC Area clearance · DI DDC install · CB Cabling · CC Continuity · DT DDC term. · FT Field term. · FD Field devices
Panel IDAreaLevelBCCStagesCurrent statusPowerT&CGraphics
Why this matters: the tracker counts a stage as done only when its cell is filled bright green, and nothing checks that colour against the WIR text. The items below make the summary figures slightly wrong. Fix them in the Excel file, then refresh the dashboard.
SeverityCategoryPanel IDAreaLevelExcel rowWhat's wrong